It's not unusual for non-engineering folk to inquire about engineering estimates and the amount of time they take. What methodology does your engineering team use to facilitate estimating when there is significant time pressure?

Where am I?

In Product Collective Answers you can ask and answer questions and share your experience with others!

Parametric estimates are usually the best compromise between speed and accuracy. We were able to define a model with +/- 50% contingency that a Principal BSA or an experienced Sr. Product Mgr can use to give a rough estimate in 5 minutes for front-end developments by identifying teams impacted, type of development and 2 or 3 other parameters. Good enough for quick "continue to deep dive or not worth the effort" decisions.

Dan Mishra
Director of Product Management

We typically do "t-shirt" sizing for "epics". xS,S, M, L, xL. These represent a range of number of sprints (2-week sprints).

If we are estimating large initiatives we tend to use "squad quarters".